You have just created a new VLAN on your network for inter-VLAN routing.
What is one step that you should include in your VLAN-based implementation and verification plan?()
A.Verify that different native VLANs exist between two switches for security purposes.
B.Verify that the switch is configured to allow for trunking on the switch ports.
C.Verify that each switch port has the proper IP address space assigned to it for the new VLAN.
D.Verify that the VLAN virtual interface has been correctly created and enabled.
您可能感興趣的試卷
你可能感興趣的試題
You have just created a new VLAN on your network.
What is one step that you should include in your VLAN-based implementation and verification plan? ()
A.Verify that trunked links are configured to allow the VLAN traffic.
B.Verify that the switch is configured to allow for trunking on the switch ports.
C.Verify that each switch port has the correct IP address space assigned to it for the new VLAN.
D.Verify that different native VLANs exist between two switches for security purposes.
You have just created a new VLAN on your network.
What is one step that you should include in your VLAN based implementation and verification plan? ()
A.Verify that different native VLANs exist between two switches for security purposes.
B.Verify that the VLAN was added on all switches with the use of the show vlan command.
C.Verify that the switch is configured to allow for trunking on the switch ports.
D.Verify that each switch port has the correct IP address space assigned to it for the new VLAN.
A.approval from senior management
B.end-user requirements
C.IEEE 802.1X authentication parameters
D.a summary implementation plan
A.Perform an incremental implementation of components.
B.Following the PPDIOO model, implement the entire solution and then test end-to-end to make sure that it is performing as designed.
C.Implement trunking of all VLANs to ensure that traffic is crossing the network as needed before performing any pruning of VLANs.
D.Test the solution on a segmented portion of a lab network prior to rolling out across the entire network.
You are planning a new VLAN-based network solution.
What is one item you should consider when creating your implementation plan as it concerns VLANs?()
A.generic router and switch configuration parameters
B.end-to-end test plan after all components have been installed and configured
C.administrator assignments
D.rollback plan
最新試題
Which three statements about STP timers are true?()
Refer to the exhibit. The command switchport mode access is issued on interface FastEthernet0/13 on switch CAT1. What will be the result?()
What must be the same to make multiple switches part of the same Multiple Spanning Tree (MST)?()
Which option correctly identifies the Cisco IOS switching methods in descending order from the fastest method to the slowest method?()
Which three statements are true of the Link Aggregation Control Protocol (LACP)?()
Examine the diagram. A network administrator has recently installed the above switched network using 3550s and would like to control the selection of the root bridge.Which switch should theadministrator configure as the root bridge and which configuration command must theadministrator enter to accomplish this?()
Refer to the exhibit. For what purpose is the command show ip cef used?()
Refer to the exhibit. On the basis of the output of the show spanning-tree inconsistentports command, which statement about interfaces FastEthernet 0/1 and FastEthernet 0/2 is true?()
What is the configured priority value of the Vlan105’s group on DS2 ?()
Refer to the exhibit. STP has been implemented in the network. Switch SW_A is the root switch for the default VLAN. To reduce the broadcast domain, the network administrator decides to split users on the network into VLAN 2 and VLAN 10. The administrator issues the command spanning-tree vlan 2 root primary on switch SW_A. What will happen as a result of this change?()