A.可留設(shè)施工縫分倉(cāng)澆筑,分倉(cāng)澆筑間隔時(shí)間不應(yīng)少于7天
B.當(dāng)留設(shè)后澆帶時(shí),后澆帶封閉時(shí)間不得少于14天
C.超長(zhǎng)整體基礎(chǔ)中調(diào)節(jié)沉降的后澆帶,混凝土封閉時(shí)間應(yīng)通過(guò)監(jiān)測(cè)確定,應(yīng)在差異沉降穩(wěn)定后封閉后澆帶
D.后澆帶的封閉時(shí)間尚應(yīng)經(jīng)設(shè)計(jì)單位確認(rèn)