()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
A.Plannedvalue B.Earned value C.Actualcost D.Costvariance
PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish
The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
A.estimating B.defining C.planning D.sequencing